Now integrated ceiling is more and more popular because of its high comprehensive performance and high cost performance. There are many materials for integrated ceiling, and the most commonly used one should be aluminum gusset ceiling. The convenience and service life of the ceiling are inextricably related to the quality of installation. So today, let's learn about the installation process of aluminum gusset ceiling. Seven steps make it easy for you to install aluminum gusset ceiling

the reason why integrated ceiling is more and more popular now is that it has high comprehensive performance and high cost performance. There are many materials for integrated ceiling, and the most commonly used one should be aluminum gusset ceiling. The convenience and service life of the ceiling are inextricably related to the quality of installation. So today, let's learn about the installation process of aluminum gusset ceiling. Seven steps make it easy for you to install aluminum gusset ceiling

installation process of aluminum gusset ceiling

1 Snap the line

first, according to the elevation horizontal line of the floor, use a ruler to vertically vector to the ceiling design elevation, snap the keel position line on the roof, and snap the elevation horizontal line of the ceiling on the wall

2. Install the main keel suspender

after snapping the elevation horizontal line and the keel position line on the ceiling, you can determine the elevation below the suspender, and then according to the keel position and the hanging spacing, fix the bolt free end of the suspender under the floor with expansion bolts, and the suspender is generally 6m reinforced

3. Install the main keel

after doing the first two works, assemble and match the nuts of the suspender, install the suspenders on the main keel in advance, and then insert the suspenders into the corresponding suspender bolts according to the position of the grading line, then screw the nuts, connect the main keel, and then install the connectors; Then adjust the elevation and straightness; Install the additional main keel at the opening, and set and connect it firmly

4. Install the secondary keel

place the triangular hanger of the secondary keel according to the snapped secondary keel grading line, and use wood keel. Generally, the spacing of the secondary keel is 600mm; According to the spacing of the main keel specified in the design, hang the secondary keel on the main keel through the triangular pendant; If the length of the secondary keel needs multiple continuous extensions, the secondary keel connectors can be used to connect, straighten and fix while hanging the secondary keel

5. Install the side aluminum strip

the general specification of the side aluminum strip is: 25mm*25mm. The elevation of the ceiling installation requires that the side aluminum strip be fixed with cement nails around the wall

6. Install the aluminum gusset plate

when installing the ceiling aluminum gusset plate, it should be gently pressed in the order of the flanging part. After completely clamping both sides of the square plate into the secondary keel, it should be pushed tightly. It must not be rough and compulsory loading and unloading, and then clamp the edge aluminum strip, straighten it, and fix the edge aluminum plate

7. Install lamps and vents

generally, the plan will be designed before the ceiling is installed, so finally, the lamps and vents should be arranged according to the ceiling plan; When installing the aluminum gusset plate, open holes according to the size of the lamps and vents to install lamps and ventilation

editor's summary: the above is the introduction of the installation process of aluminum gusset ceiling. After reading this article, you should have a more comprehensive understanding of the installation of aluminum gusset ceiling. I hope this article can help you install aluminum gusset ceiling more perfectly